Overview

 

As part of the Monroe County Water Authority’s (MCWA) Eastside Water Supply Project (ESWSP) construction will be starting on a 48" diameter transmission main in the east Webster area.

 

The 48” transmission main being constructed in the Ridge Road / State Road area will convey drinking water from the new water treatment plant to the exising transmission and distribution system.  The water main will run south, from an existing transmission main located on Ridge Road east of Salt Road to State Road.  The main will run cross-country on permanent easements and highway right-of-way.

During the first phase of work, surveyors will work along the pipeline route to mark out easements (work) limits.  The second phase of work includes the actual water main installation.  The mains will be installed parallel to each other and approximately 10 feet apart.  Additional appurtenances such as valves and air release facilities are also installed at this time.  After installation, during the third phase of work, the mains are pressure tested to check for leaks.  The mains are then flushed and tested by the Health Department before they are ready to be put into service.  The final phase of work is final restoration in which disturbed areas are restored to their preconstruction conditions.  Temporary asphalt is removed and replaced with permanent asphalt and lawn and field areas are graded and seeded.  The contractor is responsible for getting all seeded areas to grow properly.

Schedule

The schedule depends on a number of factors, but we anticipate construction beginning in late November and lasting through the end of May 2013.  Restoration should be complete by mid June of 2014. 

 

Questions

You can contact our Customer Service department at (585) 442-7200 weekdays from 8:30 am to 4:30 pm, or our Dispatcher at (585) 442-2009 weekdays before 8:30 and after 4:30 pm, and on weekends and holidays.  A Water Authority inspector will be onsite throughout construction.  Our inspectors carry an ID card and drive a vehicle with a Water Authority logo on it.  They are happy to answer any questions you may have.

Project Bulletin

Click below for a project bulletin with further information on this project.

Project Info Bulletin